Home / Projects / Al Mada

Al Mada · Parking Rehabilitation & Epoxy Flooring

Client IFM Facilities Management LLC Location Al Mada, Al Ain Division Epoxy · Civil

A complete parking-area rehabilitation and floor-coating package delivered for IFM Facilities Management at Al Mada, Al Ain, concrete repair, a high-performance Sika epoxy flooring system and full reflective traffic marking, completed in 45 days.

Project Facts

Client
IFM Facilities Management
Area
3,100 m² parking area
System
Sika repair + epoxy flooring
Duration
45 days

Repair, Coat & Mark Out

Cracked and damaged concrete flooring was repaired using Sika repair chemicals and epoxy filler, followed by surface preparation, one coat of Sika floor sealer (primer), an anti-slip coating and two coats of Sika epoxy floor paint, a durable, abrasion-resistant finish suitable for trafficked parking areas.

The package included reflective traffic marking works, parking bay lines, directional arrows, numbering and guidance markings, with kerbstones repainted to specification and parking-area walls finished in two coats of Sika Fenomastic paint. The site was handed over after comprehensive cleaning, with all construction waste disposed of in accordance with Abu Dhabi Municipality (ADM) regulations.

Project Detail

Commercial · Facilities Management

Scope of Work

  • Parking area rehabilitation
  • Epoxy flooring installation across 3,100 m²

Technical Details

  • 3,100 m² parking area
  • 45-day programme

Materials & Specifications

  • Sika repair system
  • Epoxy flooring system

Engineering Approach

Works phased across the parking area to maintain partial access for the facility during the 45-day programme, with the repair-then-coat sequence following the specified Sika system build-up.

Quality & Inspection

Inspected at agreed hold points under a project ITP, incoming material verification, staged workmanship inspections and dimensional checks, closing out with a documented handover file: test records, as-builts and applicable warranties. See Quality & HSE for the full framework.

Results & Outcome

3,100 m² of parking structure rehabilitated and recoated within the 45-day programme, substrate repairs completed to the specified Sika system, epoxy floor coating applied, and reflective traffic markings reinstated at handover.

Gallery

Highlight
3,100 m² covered
Highlight
45-day turnaround