RCC Wheel Stopper Programme
A repeat-order programme: more than 1,300 precast RCC car wheel stoppers supplied, installed, aligned and finished across three Abu Dhabi sites, much of it executed in night-time operations under CID permits secured and managed by the Costro project team, so live parking areas stayed open during the day.
Project Facts
Installed at Night, Open by Morning
The scope comprised precision installation of precast RCC wheel stoppers including foundation works, followed by application of high-durability epoxy-based road-marking paint to improve parking organisation and operational safety.
All works were programmed as night-time operations to minimise disruption to facility users, with the required CID permits obtained and administered by our team as part of the package, so the client’s operations continued uninterrupted throughout.




Delivered Across Three Sites
331 Units
Precast RCC wheel stoppers supplied and installed across the marina parking areas. Executed entirely in night-time operations under CID permits, completed in 45 working days.
934 Units
Replacement of customised RCC wheel stoppers across the Grand Prix and Fashion parking areas, delivered as part of a wider facility package. See the full Yas Mall project.
63 Units
Heavy-duty RCC wheel stoppers supplied, installed, aligned and finished to road-marking standard paint within a 15-day programme.
Project Detail
Scope of Work
- Supply & install 1,328 precast RCC wheel stoppers across three sites
- Foundation works and precision setting-out
- Road-marking standard paint finish
- Night-shift works under CID permit
Technical Details
- 1,328 precast RCC units total
- Marsa Al Bateen: 331 units · 45 working days
- Yas Mall: 934 customised units
- Saadiyat Retail: 63 units · 15 days
- Night-shift execution under CID permit
Materials & Specifications
- Precast RCC wheel stoppers
- High-durability epoxy-based road-marking paint
Engineering Approach
Night-works methodology used throughout to avoid disruption to live, operating facilities · CID permits were obtained and administered by our own team as part of the package, so parking areas reopened each morning. Repeat orders across three sites let us standardise the precast unit, setting-out method and paint finish between deployments.
Quality & Inspection
Inspected at agreed hold points under a project ITP, incoming material verification, staged workmanship inspections and dimensional checks, closing out with a documented handover file: test records, as-builts and applicable warranties. See Quality & HSE for the full framework.
Results & Outcome
More than 1,300 precast RCC wheel stoppers delivered across three Abu Dhabi facilities, each site completed within its programme and handed back without interrupting daytime operations.