Al Maqam Palace · Interlock Paving & Kerbstone Works
Approximately 650 m² of interlock paving and external works at Al Maqam Palace, a 4-metre-wide pathway road, precast concrete kerbstones, paving to the front of the garage area and 27 new garden lights, delivered and handed over within a 30-day programme.
Project Facts
Private estate — client details withheld for confidentialityInterlock Paving
80 mm single-colour blocks to the approved layout.
Pathway Road
New roadway built up from subgrade to finished surface.
Road Base
Supplied, watered and mechanically compacted.
Garden Lights
On concrete foundations along both sides of the roadway.
Pathway Road & Precast Kerbstones
A 4-metre-wide pathway road built up layer by layer, edged with precast concrete kerbstones for long-term durability.
Works began with the removal of existing loose soil, site levelling and preparation of the subgrade. A 200 mm thick road base was supplied, watered and mechanically compacted, followed by a compacted black sand bedding layer to provide a stable foundation for the paving works.
Precast concrete kerbstones were then supplied and installed over PCC bedding with a polyethylene separation sheet, completed with concrete haunching to ensure proper edge restraint and lasting alignment.







Interlock Paving Works
Approximately 650 m² of 80 mm thick, single-colour interlock paving to the pathway road and the front of the garage area.
Interlock blocks were installed in accordance with the approved layout over the prepared bedding, then finished with sand filling and mechanical compaction to achieve a level, durable pavement surface, completed to the required quality and safety standards.



Garden Lighting
27 garden lights supplied and installed on both sides of the roadway to complete the external landscape.
Lights were set out at 6-metre intervals, each mounted on a 250 × 250 × 400 mm concrete foundation for reliable long-term support, with the associated electrical preparation works carried out alongside the civil scope.



Project Detail
Scope of Work
- Interlock paving across ≈650 m²
- Installation of 27 garden lights at 6 m intervals
- Associated kerbstone works
Technical Details
- ≈650 m² interlock paving
- 80 mm paving blocks
- 27 garden lights at 6 m spacing
- 30-day duration
Materials & Specifications
- 80 mm interlock paving blocks
Engineering Approach
Paving levels and falls were set out to tie into existing drainage and hardscape before block-laying, with garden lighting positions coordinated to the landscape design.
Quality & Inspection
Inspected at agreed hold points under a project ITP, incoming material verification, staged workmanship inspections and dimensional checks, closing out with a documented handover file: test records, as-builts and applicable warranties. See Quality & HSE for the full framework.
Results & Outcome
≈650 m² of 80 mm interlock paving with precast kerbstones and a 4 m pathway road completed in 30 days, sub-base prepared and compacted, levels and falls set out to existing drainage, and 27 garden lights installed at 6 m centres.